I have spent some time completing a worklist audit on Seaventures and I’m getting a bit concerned I will not be able to complete all this on my own to get started at the end of April.

I really could do with some help if anyone has the time. Against each job below I have estimated the number of people and time it will need to complete these. Many of the jobs requiring people will take 4 times as long if I have to do it on my own and some will be impossible, so some voluntary help would be greatly appreciated.

If you have some time to spare could you let me know which job you feel you could do and the time/date you could spare I can then ensure all the necessary equipment is ready for you.

Thanks in advance - Geof



* Loosen, renew sealant under guardrails and other fittings and re-secure. Two people 2 days
* Replace guardrail wires 1 person – 1 hour
* Renew life lines 1 person – 1 hour
* Sand down and apply new seasonal coat of paint to the topsides. Two people – 2 days
* Tune new fixed rigging Two people – 2 x 1 day
* Set out new system for new running rigging and replace ropes Two people – 1 day
* Freshen internal lockers with a coat of locker paint. Two people – 2 Days
* Repaint saloon and companionway steps with non- slip paint one person x 2days
* Sand and re-varnish internal woodwork 1 person x 1 day
* Re connect instrument and lighting wiring 1 person x 1 day
* Help finish internal decorations 2 people x 2 days
* Help finish installation of new hatch garage system 2 people x 2 days
* Help with GRP work for installation of new larger winches 2 people x 1 day
* Check and replace worn serviceable marine diesel engine parts 1 person x 1 day
* Set up spares and tools kit for engine. 1 person x ½ day